Delay Recovery Analysis At Rob

Impact Factor
7.883
Call For Paper
Volume 12 Issue 07

July 2026

Download Paper Format
Copyright Form
Share on:

Author(s)

Shraddha S. Bendsure Prof. Basavaraj S. Balapgol Ashwini R. Patil

Abstract

The Case Study Considered Here Is A Railway Over Bridge Project At Akurdi, Pune. The Site Is Lagging Behind By 8 Months According To The Monthly Progress Report Worked Out By The Contractor. Analysis Has Been Done Keeping In Mind The Equipments And Manpow


Keywords

Equipment Management Manpower Management Estimation Scheduling Quality.